Miami-Dade Recertification
Sunny Isles Beach’s Building Department lists what a recertification filing must contain and issues the repair permits. One team delivers the complete recertification, on the forms the department posts.
- Engineer
- Juan Tercero, PE., M.Sc. · Florida PE 105256
Your city
How building recertification is handled in Sunny Isles Beach
Sunny Isles Beach runs the recertification through its Building Department. The department’s page sets out what owners submit once the notice arrives, what happens when repairs are needed and how an extension is requested. It does not say where the package is handed in, so what follows marks both what the city has published and what it leaves open.
- The notice
- The city’s page says owners of properties that require recertification receive a Notice of Required Recertification, which starts the process; further on it writes Notice of Required Inspection. It does not say who sends it in Sunny Isles Beach, or how. Keep the letter: the page counts the owner’s time from its date, and the days in force are in the rows further down.
- Filing the report
- The city’s list of what to submit names a structural inspection report and an electrical inspection report, each signed and sealed, with copies, and asks that every form carry an original signature and a seal. The page names no portal or counter for the package, so we confirm with Sunny Isles Beach’s Building Department how it wants it delivered.
- The city’s forms
- The Building Department’s documents page has a section headed Building Recertification Forms, with a structural form, an electrical form and a general considerations and guidelines document. Those guidelines say the forms provided must be used and that proprietary forms are not accepted. The city ties both reports to the minimum inspection guidelines required by the Miami-Dade County Board of Rules and Appeals.
- What goes with it
- The same section posts two parking-lot documents, one on guardrails and one on illumination; each belongs in the package only where it applies to the property.
- Repairs
- Before any repair, the city’s page says, the owner hires a Florida licensed contractor and obtains permits from the Building Department; its permits page says every application is filed online, through a portal account. Once every permit passes final inspection, the recertification page calls for a signed and sealed report stating that the repairs are complete and the building is safe for continued use.
- Extensions
- The city’s page says the Building Official may grant an extension, up to a limit it states, to submit the report or to obtain the permits. It takes a written request from the professional, with a signed and sealed statement that the building may continue to be occupied while it undergoes recertification. Sunny Isles Beach’s page does not say where that request is sent.
- If it is late
- Sunny Isles Beach’s page says a property whose recertification is not obtained in time is referred to the Unsafe Structures Section and an enforcement case is opened. That section then monitors the process, and the page lists posting the building unsafe, a Notice of Violation, referral to the Unsafe Structures Board and orders to vacate among its steps.
- A second notice
- The same city page covers the recertification of structural glazing: owners of threshold buildings with an exterior façade of structural sealant glazing must have that façade inspected at intervals, and they receive a notice with its own name, the Notice of Required Recertification of Structural Glazing for Threshold Buildings. Read the title on your letter to see which of the two you hold.
Building office City of Sunny Isles Beach Building Department Government Center, 3rd Floor 18070 Collins Avenue Sunny Isles Beach, FL 33160 Phone: (305) 947-2150
Read on the website of the City of Sunny Isles Beach Building Department:
When it applies
The deadlines that apply in Sunny Isles Beach
The schedule is Miami-Dade County’s, printed here for a building in Sunny Isles Beach; the date on your own notice is the one that counts.
- First due in Sunny Isles Beach: At 30 years — 25 for condominium and cooperative buildings of three or more stories within 3 miles of the coast.
- Then in Sunny Isles Beach: Every 10 years, for the life of the structure.
- Time to file in Sunny Isles Beach: 90 days from the Notice of Required Inspection.
- If repairs are needed in Sunny Isles Beach: 150 days from the Notice to finish repairs that need no permit and to obtain permits for the rest.
- Condominiums & co-ops in Sunny Isles Beach: The recertification serves as compliance with the state milestone inspection — no separate milestone report is filed.
Miami-Dade County’s rows, for Sunny Isles Beach. Source: Code of Miami-Dade County, Section 8-11(f) · Last verified:
Questions & answers
Questions boards in Sunny Isles Beach ask
What do we do first with a Notice of Required Recertification in Sunny Isles Beach?
The city’s page says that notice is what starts the process; what it asks owners to submit is a structural inspection report and an electrical one. How long you have is in the rows above, counted from the date on the notice. A phone photo of the letter is enough for us to read it and confirm what Sunny Isles Beach’s Building Department is asking for, and by when.
How do we file the recertification report in Sunny Isles Beach?
The city’s page lists what goes in but not where or how to hand it in: it names no portal, counter or mailbox for a recertification report, although permit applications in the city are filed through an online portal account. Nor does the Sunny Isles Beach page describe the review that follows. We confirm the route with the city’s Building Department before the package goes in.
What happens in Sunny Isles Beach if the recertification is late?
The city’s page says the property is referred to the Unsafe Structures Section and an enforcement case is opened. It names what that can include: the building posted as unsafe, a Notice of Violation, referral to the Unsafe Structures Board, orders to vacate. Is the date on your Sunny Isles Beach notice already behind you? Send it all the same; the page says the recertification process goes on under that section’s watch.
Can we ask Sunny Isles Beach for more time to file the recertification report?
The city’s page allows for it, within a limit it sets: the Building Official may grant an extension to submit the report or to obtain the permits. The request is made in writing by the professional and must include a signed and sealed statement that the building may continue to be occupied while it undergoes recertification. A letter from the board alone is not what the Sunny Isles Beach page describes.
Is Sunny Isles Beach’s recertification the same as the 40-year recertification?
Yes: the 40-year recertification is the former name of the program Sunny Isles Beach’s Building Department runs today. The city’s page uses that name when it speaks of earlier inspections: it says buildings built up to a cut-off year that already had a first inspection through “Miami-Dade’s 40-Year program” continue on their established schedule. For a Sunny Isles Beach building today, the ages in force are the county’s, in the rows above.
One team
The complete recertification for a building in Sunny Isles Beach
Next step
Send us your Notice of Required Recertification — a phone photo is enough — or, with no notice yet, the building’s address and the year built. We confirm what the City of Sunny Isles Beach Building Department is asking for and by when, and reply with a proposal for the complete recertification.
Next step
A county notice in your hand, a building that worries you or a new project — describe it and attach what you have. A phone photo of the letter is enough. You hear back from the engineer, with questions or with a written proposal.
The proposal is free. We usually reply within two hours.