Miami-Dade Recertification

Building Recertification in Miami Gardens

The city’s Building Services lists recertification among its services and posts its own report forms. One team delivers your Miami Gardens recertification complete, on those forms.

Engineer
Juan Tercero, PE., M.Sc. · Florida PE 105256

Your city

How building recertification is handled in Miami Gardens

The city’s website has no page of its own that explains the recertification. What it has is this: City of Miami Gardens Building Services lists the program among its services, and its Documents and Forms page keeps a Recertification group with the city’s report forms, the county’s guidelines and an extension request. The county’s deadlines for a Miami Gardens building are in the rows below.

The notice
The city’s website does not say who sends the Notice of Required Inspection, or how it reaches the owner. On the site the notice appears only as a date to fill in: the city’s structural report form asks for the date of that notice, and its extension request has a line marked Notice Date. Keep the letter, so the date is at hand.
The city’s forms
Miami Gardens lists its own structural and electrical report forms — each titled with the city’s initials, CMG — in the Recertification group of its Documents and Forms page. The guidelines in that group are Miami-Dade County’s; they say the approved report forms must be used and that proprietary forms will not be accepted.
What goes with them
The city also posts two certifications for the parking lot — illumination and guardrails — which are filed where they apply to the property. The guidelines ask for a cover letter with each report, and the electrical form has a section for infrared thermography, where the building’s electrical service requires it, with the thermography report attached.
Filing the report
The page that lists these forms opens with one general instruction: building forms are to be completed and submitted as attachments to an online permit application in CSS, the city’s Citizen Self Service portal, as required. The site has no filing instruction written for the recertification report in particular, so we confirm with Building Services how yours is to be filed before anything goes in.
After filing
The city’s site does not describe its review or say how an owner learns the result. The county guidelines it posts say that recertification reports may be audited, that the building may be inspected at the discretion of the Building Official, and that the Building Official keeps the right to revoke an approved report.
Repairs
The guidelines Miami Gardens posts say that repairs the report identifies will most likely need permits, that proceeding without them may lead to a code violation, and that repairs under a permit afford additional time to comply. The city’s structural form has a box for the amended report, after completion of repairs, and asks whether the building can remain occupied while they are ongoing.
Extensions
The city has its own form, titled Recertification Extension Request. It is written as a letter from the owner, the owner’s agent or the contractor that gives the reasons for the request, and it is sworn before a notary. A line on it records the number of days granted; the site does not say where the form is sent.
Older names
The Building Services page still lists the program as “40 Year Re-Certifications”, and the city’s extension request still calls it the 40-year recertification. The report forms the city posts say building recertification, and that is the program meant. The ages and the days in force are the county’s, in the rows further down.

Building office City of Miami Gardens Building Services 18605 NW 27th Avenue Miami Gardens, FL 33056 Phone: (305) 622-8027

Read on the website of the City of Miami Gardens Building Services:

When it applies

The deadlines that apply in Miami Gardens

The schedule is Miami-Dade County’s, printed here for a building in Miami Gardens; the date on your own notice is the one that counts.

  • First due in Miami Gardens: At 30 years — 25 for condominium and cooperative buildings of three or more stories within 3 miles of the coast.
  • Then in Miami Gardens: Every 10 years, for the life of the structure.
  • Time to file in Miami Gardens: 90 days from the Notice of Required Inspection.
  • If repairs are needed in Miami Gardens: 150 days from the Notice to finish repairs that need no permit and to obtain permits for the rest.
  • Condominiums & co-ops in Miami Gardens: The recertification serves as compliance with the state milestone inspection — no separate milestone report is filed.

Miami-Dade County’s rows, for Miami Gardens. Source: Code of Miami-Dade County, Section 8-11(f) · Last verified:

Questions & answers

Questions boards in Miami Gardens ask

Who sends the recertification notice in Miami Gardens?

The city’s website does not say who sends it or how. It does show that City of Miami Gardens Building Services lists recertification among its services, and that the city’s report form asks for the date of the Notice of Required Inspection. Your letter settles the question: a phone photo of it is enough for us to read what it asks for and by when.

How do we file a recertification report in Miami Gardens?

The site gives no instruction of its own for the recertification report. The city’s forms page says its building forms are to be submitted as attachments to an online permit application in CSS — the Miami Gardens Citizen Self Service portal — and the county guidelines posted there say the initial report should go to the local jurisdiction as soon as it is completed. We confirm the route with Building Services before the complete recertification goes in.

How do we request a recertification extension in Miami Gardens?

The city has a form for it, titled Recertification Extension Request. It is a letter from the owner, the owner’s agent or the contractor that states the reasons, has a line marked Notice Date and is sworn before a notary. The form also has a line for the days granted; the site does not say how long an extension runs or where the form is delivered, so that is a question for Building Services.

What happens in Miami Gardens if the recertification report is late?

The city’s website does not say. What the city does publish is a form to request an extension. If the date on your letter has passed, send the letter anyway — the work starts with the inspection and the report either way.

Is Miami Gardens’ recertification the same as the 40-year recertification?

Yes. The Building Services page still lists it as “40 Year Re-Certifications”, and the city’s extension request still uses that name, while the report forms the city posts carry the title Building Recertification Inspection Report Form. It is Miami-Dade County’s program, with the county’s guidelines posted among the city’s forms; the ages in force today are in the rows above.

One team

The complete recertification for a building in Miami Gardens

Next step

Send the letter about your Miami Gardens building — a phone photo is enough — or, with no letter yet, the address and the year built. We read it, confirm what Building Services is asking for and by when, and reply with a proposal for the complete recertification.

The package, part by part

Next step

Tell us about the building. We reply with a scope.

A county notice in your hand, a building that worries you or a new project — describe it and attach what you have. A phone photo of the letter is enough. You hear back from the engineer, with questions or with a written proposal.

The proposal is free. We usually reply within two hours.