Miami-Dade Recertification
Miami Beach’s Building Department posts the recertification notice at the property and reviews the report. One team delivers the complete recertification, in the single report the city asks for.
- Engineer
- Juan Tercero, PE., M.Sc. · Florida PE 105256
Your city
How building recertification is handled in Miami Beach
In Miami Beach the recertification runs through the City of Miami Beach Building Department, in the unit its written procedure calls the Recertification Section. The department posts the notice at the building, receives a digitally signed report through its Citizen Self Service portal or by e-mail, and reviews it before the Building Official gives final approval. Its page still gives the program’s former name, the 40-year recertification.
- The notice
- The Building Department posts a notice at the property well ahead of the date the recertification is due. Reminders follow as that date approaches, the final one together with a notice posted on site. The recertification package asks the owner to arrange an electrical and a structural inspection of the building and to file a signed and sealed report with the Recertification Section.
- Filing the report
- The city asks for one completed inspection report that contains both the structural and the electrical reports. A digitally signed report can go in through the Citizen Self Service portal — CSS on the city’s pages — or by e-mail to the Building Recertification team. The city’s procedure adds that an e-mailed report should carry a digital signature and seal that a third party can verify.
- In person
- A report that is not digitally signed and sealed may be e-mailed as a scanned copy, the city’s procedure says, with the original signed and sealed report sent by mail or handed in at an in-person appointment at the Building Department. The department’s procedures also list Building Recertification among its appointment services, and the phone line has an option under the same name.
- The city’s forms
- Under “Required Building Recertification Reporting Forms” the city’s page lists a structural and an electrical inspection form, both under the Building Department’s name, a structural inspection guide, and two parking-lot forms — guardrails and illumination — that go in where they apply. The electrical form has a thermography section, with the thermography report attached where the building’s electrical service requires one.
- After filing
- The city’s procedure routes the report to the Chief Structural Engineer and the Chief Electrical Inspector for review. After both approvals the recertification goes to the Building Official for final approval. The city’s page says the Building Official then issues a Building Recertification approval letter, sent to the owner and to the engineer or architect of record.
- Repairs
- When the first report notes deficiencies that need permits, the city’s page has the owner submit an updated report once those permits have passed final inspection. The same paragraph requires a cover letter certifying that the building is structurally and electrically safe for its specified use and occupancy. The procedure says the department fast-tracks those repair permits; the recertification number goes on the permit application.
- Extensions
- The city’s procedure says an extension to obtain repair permits may be granted when the design professional who inspected the building finds it poses no harm to its occupants, states in writing that it can stay occupied and asks for the extension. The procedure sets its own length for it; the time for repairs now in force is the county’s, in the rows below.
- If it is late
- The procedure describes a reminder posted on site — it calls it a Red Tag — when the report has not reached the Building Department by a set point. If neither the report nor an extension letter is in on time, it says, a recertification violation is issued: the Notice of Violation is posted on the building and a copy goes to the owner by certified mail.
Building office City of Miami Beach Building Department 1700 Convention Center Drive, Second Floor Miami Beach, FL 33139 Phone: (305) 673-7610
Read on the website of the City of Miami Beach Building Department:
When it applies
The deadlines that apply in Miami Beach
The schedule is Miami-Dade County’s, printed here for a building in Miami Beach; the date on your own notice is the one that counts.
- First due in Miami Beach: At 30 years — 25 for condominium and cooperative buildings of three or more stories within 3 miles of the coast.
- Then in Miami Beach: Every 10 years, for the life of the structure.
- Time to file in Miami Beach: 90 days from the Notice of Required Inspection.
- If repairs are needed in Miami Beach: 150 days from the Notice to finish repairs that need no permit and to obtain permits for the rest.
- Condominiums & co-ops in Miami Beach: The recertification serves as compliance with the state milestone inspection — no separate milestone report is filed.
Miami-Dade County’s rows, for Miami Beach. Source: Code of Miami-Dade County, Section 8-11(f) · Last verified:
Questions & answers
Questions boards in Miami Beach ask
Who sends the recertification notice in Miami Beach?
The City of Miami Beach Building Department. Its procedure says Miami-Dade County provides the list of buildings that require recertification and that the list is reviewed before the notices go out. The report goes back to the department’s Recertification Section. A phone photo of the notice posted at your building is enough for us to confirm what it asks for and by when.
How do we check the recertification status of a building in Miami Beach?
On the city’s Citizen Self Service portal. The recertification page explains the search: look under permits, choose “Existing Building Recertification” as the permit type and enter the building’s address. That record is part of the building’s history we read, along with the notice, before we reply with a proposal for the complete recertification.
Can a building in Miami Beach be recertified with open permits or violations?
Not under the city’s procedure. It says a building recertification cannot be approved if the property has open building violations and open or expired permits. The procedure’s Letter of Building Recertification is issued when, among other conditions, none of those remain and the reports are approved. That is one reason we read the building’s history before proposing anything.
What does Miami Beach do when a recertification report is not filed on time?
The city’s procedure says a building recertification violation is issued and, if it is not complied with within the notice period, forwarded to Miami Beach’s Special Master. It adds that non-compliance sends the case on to the Miami-Dade County Unsafe Structure Board and may end in an order to demolish the structure and the need to vacate the building. The city’s violations page says Special Magistrate hearings are held in person at City Hall.
What is the annual maintenance log that Miami Beach asks building owners for?
It is a yearly log of routine structural repairs. Miami Beach’s recertification page links to what it calls the mandatory annual maintenance log. The log’s page says owners submit it by a deadline that depends on the building’s address, on the Citizen Self Service portal under the Annual Maintenance Log application, and that not every building has to file.
One team
The complete recertification for a building in Miami Beach
Next step
Send us the notice from Miami Beach’s Building Department — a phone photo is enough — or, with no notice yet, the building’s address and the year built. We confirm what the Recertification Section is asking for and by when, and reply with a proposal for the complete recertification.
Next step
A county notice in your hand, a building that worries you or a new project — describe it and attach what you have. A phone photo of the letter is enough. You hear back from the engineer, with questions or with a written proposal.
The proposal is free. We usually reply within two hours.