Skip to content

BSIP

Building Safety Inspection (BSIP) in Pembroke Park

Pembroke Park has a BSIP submittal application of its own, with a checklist of what goes with it. Already late? One team still delivers the complete BSIP inspection and report, put together the way the Town’s packet lists it.

Building office
Town of Pembroke Park Building Department

The county’s clock · in Pembroke Park

  1. 25 years

    First due, from the certificate of occupancy — in Pembroke Park

  2. 10 years

    Then again, every cycle after — in Pembroke Park

  3. 180 days

    To file, from receiving the Notice — in Pembroke Park

  4. 180 days

    To repair, from the date of the report — in Pembroke Park

When it applies

The deadlines that apply in Pembroke Park

For a building in Pembroke Park, these are the dates that count, and an unanswered notice does not go away.

  • First due in Pembroke Park: At 25 years, counted from the certificate of occupancy.
  • Then in Pembroke Park: Every 10 years.
  • Time to file in Pembroke Park: 180 days from receiving the Notice of Required Inspection. Older guides still say 90 days; the policy in force since August 9, 2024 gives 180. The letter you received states its own date.
  • If repairs are needed in Pembroke Park: 180 days from the date of the report, under permit, unless the Building Official sets a different time.
  • Condominiums & co-ops in Pembroke Park: The BSIP report serves as phase one and phase two of the state milestone inspection.

Broward County’s rows, for Pembroke Park. Source: Broward County Board of Rules and Appeals, Policy #05-05 · Florida Building Code, Broward County Amendments, Section 110.15 · Last verified:

Your city

How the Building Safety Inspection Program runs in Pembroke Park

In Pembroke Park the Building Safety Inspection Program (BSIP) runs through the Town of Pembroke Park Building Department, at Town Hall. The Town’s program page is a set of documents: a master packet, the Town’s own submittal application, the county’s uniform permit application, a Property Appraiser report, the Board of Rules and Appeals’ policy and the two inspection forms.

The Town’s application
Pembroke Park’s Building Safety Inspection Report Submittal Application asks for the property’s folio number and the building’s square footage, the owner or association and its agent, and the licensed professionals on the job — a structural engineer or architect first, a second engineer or architect after. Its application type marks the inspection cycle, or a Repairs Required Submittal.
Its checklist
At its top, the Town’s application lists what the package must include: the Broward County Uniform Building Permit Application, the structural and the electrical Building Safety Inspection Report Forms, the Broward County Property Appraiser’s report and a cover letter from the architect or structural engineer, with repair recommendations where they are required.
The notice number
The Town’s application has a line for the tracking number from the notification, so the letter is worth keeping. Pembroke Park’s program page does not say who sends it; the Board’s policy posted there has the Building Official notify the owner or association by certified mail, return receipt, once the county’s yearly list arrives.
The master packet
The BSIP Master Packet on the Town’s page starts with the submittal application and continues with pages that mark where each piece goes, among them one headed for the Property Appraiser report to be inserted. Filed in that order, the package reaches the Building Department the way the Town lays it out.
Sending it now
The Town says it is moving its permitting from Gov-Easy to a new online system with CivicPlus, and the old system is offline for self-submissions. Until the change is complete, its Online Permitting System page has applications, forms and required documents e-mailed to the Building Department, each with a Building Department Transmittal Form; without one, a submission is returned.
Repairs
When the report calls for repairs, the Town’s application has a Repairs Required Submittal type, with room for the permit numbers of the repairs, and its checklist asks for the repair recommendations in the cover letter where required. The program page says nothing more about repairs, so the Building Department sets the steps after them.
The policy posted
The Board of Rules and Appeals’ policy on Pembroke Park’s page is the edition in force for the county. The times in the rows above come from it; the page itself adds no time of its own and describes no extension.

Building office Town of Pembroke Park Building Department 3150 SW 52nd Avenue Pembroke Park, FL 33023 Phone: (954) 966-4600

Read on the website of the Town of Pembroke Park Building Department:

What the BSIP inspection includes in Pembroke Park

  • Structural inspection
  • Electrical inspection
  • Garages & parking lots
  • Balconies, docks & seawalls
  • Tests only where needed

Who does each step

The fee

  1. From $2,000

    Fixed fee, by building size — Pembroke Park BSIP

    Small commercial or multifamily building

  2. 3–4 days

    Signed Pembroke Park BSIP package, after the inspection

    Urgent? 1–2 days.

  3. Free

    The written proposal

Most buildings fall in a range by size. The fixed fee for your Pembroke Park BSIP is written in the proposal, before any work starts.

Questions & answers

Questions boards in Pembroke Park ask

What does Pembroke Park ask for with a BSIP report?

The Town’s own submittal application, plus the Broward County Uniform Building Permit Application, both Building Safety Inspection Report Forms, the Property Appraiser’s report and a cover letter from the architect or structural engineer, carrying repair recommendations where required. The complete BSIP inspection and report we deliver is assembled against that checklist.

How do we send a BSIP package to Pembroke Park right now?

By e-mail to the Building Department, with a Building Department Transmittal Form, while the Town moves from Gov-Easy to its new CivicPlus system; its page says a submission without that form is returned without further processing. The transmittal form itself also offers hand delivery and mail, so we confirm with the Town which route it wants for the BSIP.

Who sends the BSIP notice in Pembroke Park?

The Town’s program page does not say. The Board’s policy it posts has the Building Official notify the owner or association by certified mail, return receipt, after the county’s yearly list arrives, and the Town’s application asks for the tracking number from that notification. A picture of the letter taken with a phone is all we need to read it.

How long do we have to file the BSIP report in Pembroke Park?

The times are Broward’s, shown above under “Time to file” and “If repairs are needed”, and they come from the Board’s policy that the Town posts. Pembroke Park’s page adds no extension procedure of its own. If the date on your Pembroke Park letter is close, send it to us without waiting.

Is the Pembroke Park BSIP what used to be called the 40-year recertification?

Yes. The Town’s own application still offers the 40-year label as one of its inspection types, beside the first inspection and the later cycles, and the program page calls the form a recertification application. It is one program; the ages that apply now are listed in the rows above.

What to send

The complete BSIP inspection and report in Pembroke Park, at a fixed fee

Send the notice addressed to your Pembroke Park building — a picture will do — or, if none has come, the address and the year of the certificate of occupancy. We confirm with the Town of Pembroke Park Building Department how it wants the package and answer with a proposal for the complete BSIP inspection and report.

The package, part by part

Contact

Get in touch.

Tell us about the building and what you need from us. Write in English or in Spanish.

Attachments optional

Photographs, drawings or reports. PDF, images, DWG, DXF or ZIP, up to 25 MB each, five files.