Building Safety Inspection (BSIP) in Fort Lauderdale

Fort Lauderdale’s Building Official sends the notice by certified mail; the reports go in through the LauderBuild Plan Room, and one team delivers the complete BSIP inspection and report.

Engineer
Juan Tercero, PE., M.Sc. · Florida PE 105256

Your city

How the Building Safety Inspection Program runs in Fort Lauderdale

On Fort Lauderdale’s site, Broward’s Building Safety Inspection Program (BSIP) comes under the City of Fort Lauderdale Development Services Department, and the program page gives the Building Safety Program as the contact. The notice comes from the Building Official by certified mail, and the whole filing is electronic, through the LauderBuild Plan Room. Here is what Fort Lauderdale’s own pages say, step by step.

The notice
Fort Lauderdale’s page says the notice comes from the Building Official by certified mail, to the property owner, the association or both, in the year the building is due for inspection. Keep it: the city’s submittal form asks for the tracking number from that notification.
Filing the report
Fort Lauderdale takes the filing electronically only — its page says paper submissions are no longer accepted. The documents go in through the LauderBuild Plan Room, under the application the city calls the Building Safety Inspection Program Application (BSIP). Each one is uploaded as a separate file; the page says not to combine them.
The city’s forms
The city’s page lists the forms that must be completed and attached to the application: its own Building Safety Inspection Submittal Form, a structural inspection form and an electrical inspection form. The structural form it links is headed Broward County BORA, the county’s Board of Rules and Appeals. The Plan Room’s list of document types marks both inspection forms as requiring the digital sign and seal.
The submittal form
Fort Lauderdale’s submittal form asks for the property’s folio number and the building’s square footage. It is marked either as an initial submittal or as a Repairs Required Submittal, which also asks for the permit numbers of the repairs. Its checklist names the structural and the electrical report forms as part of the package.
Signatures and files
Fort Lauderdale requires every document to be digitally signed and sealed. The city’s Digital Signature Policy does not accept a self-signed signature, and it names the certification authorities it approves for digital certificates. The Plan Room’s general standards ask for PDF files and rule out encrypted or password-protected ones.
After filing
Once the application is in, Fort Lauderdale’s page mentions one step: an e-mail notification when it has been accepted. It does not say how the owner is told the result of the review or what document closes the case. Under the Plan Room’s general rules, once a package has been submitted for review, more documents cannot be uploaded without permission from City staff.
Repairs
When repairs are needed, Fort Lauderdale’s page calls for a written, signed and sealed letter to both the owner and the Building Official, stating whether the building can stay safely occupied while they are made. Once they are finished, it has the licensed professional who did the inspection re-inspect and provide an amended report, with a signed and sealed letter confirming that all repairs are complete.
If it is late
Fort Lauderdale’s program page does not say what happens when a report is late: it names no hearing body and describes no extension of the time to file. The one exception it mentions concerns repairs, whose time — in the rows further down — applies unless the Building Official specifies otherwise. For anything else, the notice and the Building Safety Program settle it.

Building office City of Fort Lauderdale Development Services Department Phone: (954) 828-5932

Read on the website of the City of Fort Lauderdale Development Services Department:

When it applies

The deadlines that apply in Fort Lauderdale

The schedule is the Broward County Board of Rules and Appeals’, printed here for a building in Fort Lauderdale; the date on your own notice is the one that counts.

  • First due in Fort Lauderdale: At 25 years, counted from the certificate of occupancy.
  • Then in Fort Lauderdale: Every 10 years.
  • Time to file in Fort Lauderdale: 180 days from receiving the Notice of Required Inspection. Older guides still say 90 days; the policy in force since August 9, 2024 gives 180. Your city’s letter states its own date.
  • If repairs are needed in Fort Lauderdale: 180 days from the date of the report, under permit, unless the Building Official sets a different time.
  • Condominiums & co-ops in Fort Lauderdale: The BSIP report serves as phase one and phase two of the state milestone inspection.

Broward County’s rows, for Fort Lauderdale. Source: Broward County Board of Rules and Appeals, Policy #05-05 · Florida Building Code, Broward County Amendments, Section 110.15 · Last verified:

Questions & answers

Questions boards in Fort Lauderdale ask

Who sends the BSIP notice in Fort Lauderdale, and how does it arrive?

Fort Lauderdale’s Building Official, by certified mail. The city’s page says owners and associations receive it in the year their building is due for inspection, and the city’s submittal form later asks for the tracking number from that notification. A phone photo of the notice is enough for us to read it and confirm what Fort Lauderdale is asking for and by when.

How do we file a BSIP report in Fort Lauderdale?

Through the LauderBuild Plan Room; Fort Lauderdale no longer accepts paper. LauderBuild’s page lists a desktop computer as a minimum requirement — submission is not supported on mobile devices — and its FAQ, written for permit records, says the Plan Room opens a record only to a LauderBuild account whose contact is listed on it. The complete BSIP inspection and report we deliver goes on the forms Fort Lauderdale’s page lists.

How long do we have to file the BSIP report in Fort Lauderdale?

Both times are Broward’s and sit in the rows above: the time to file the report and the time for repairs. On repairs, Fort Lauderdale’s page adds that the time applies unless the Building Official specifies otherwise. The page describes no way to ask for more time to file, so the certified notice and the Building Safety Program settle what applies to your building.

Which buildings are exempt from the BSIP in Fort Lauderdale?

Fort Lauderdale’s page lists what is not subject to the program: federal and state government buildings, buildings on sovereign tribal lands, school buildings managed by the Broward County School Board, small residential buildings and small structures (the page sets their size limits), certain townhouses, defined by their form of ownership, and railroads and related facilities. If Fort Lauderdale’s notice reached a building you believe is on that list, send it to us with the address.

How do we correct a BSIP report already filed in Fort Lauderdale?

For resubmissions or corrections of older reports — Fort Lauderdale’s page gives the cut-off date — the corrected report goes by e-mail to the addresses printed there, not through a new application, which the page says results in duplicate records. The page gives no instruction for a report created after that date; under the Plan Room’s general rules, a package already submitted for review takes further uploads only with permission from City staff.

One team

The complete BSIP inspection and report for a building in Fort Lauderdale

Next step

Send the certified notice from Fort Lauderdale’s Building Official — a phone photo is enough — or, with none yet, the address and the year of the certificate of occupancy. We confirm what the city asks for and by when, and reply with a proposal for the complete BSIP inspection and report.

The package, part by part

Next step

Tell us about the building. We reply with a scope.

A county notice in your hand, a building that worries you or a new project — describe it and attach what you have. A phone photo of the letter is enough. You hear back from the engineer, with questions or with a written proposal.

The proposal is free. We usually reply within two hours.

info@ttcivilstructural.comMiami-Dade & Broward County, Florida